Correct option is D
Given:
Time taken by pipe A to fill the tank = 21 hours
Time taken by pipe B to fill the tank = 24 hours
Here, extra 48 minutes represents the extra time taken by the pipes due to the leak.
Solution:
Total units of water to be filled = LCM of (21, 24) = 168 units.
Pipe A can fill 8 units of water in 1 hr.
Pipe B can fill 7 units of water in 1 hr.
Normal Time is taken to fill the tank = 168/15 hrs = 11 hrs = 11 hrs 12 minutes.
With 48 min extra, the pipes would take 12 hrs to fill the tank.
Let the leakage can empty N units of water in 1 hr.
(7 + 8 - N) × 12 = 168,
15 - N = 14
N = 15 - 14 = 1
Leakage can empty 1 unit of water in 1 hr.
Leakage of 168 units of water takes 168 hrs.
Hence, the time taken to empty the tank is '168' hrs.