Correct option is A
When two alternators are connected in parallel, they must be synchronized before closing the circuit breaker. Synchronization ensures that the voltage difference across the circuit-breaker contacts is approximately zero at the instant of closing.
For successful synchronization, the following four conditions must be satisfied:
1. Equal Voltage Magnitude
The generated voltage of the incoming alternator must be approximately equal to the grid or bus-bar voltage.
If the voltage magnitudes are different, circulating reactive currents may flow between the alternators.
2. Equal Frequency
The frequency of the incoming alternator must be equal to the grid frequency.
For example, if the grid frequency is 50 Hz, the incoming alternator should also generate approximately 50 Hz.
3. Same Phase Sequence
The phase sequence of both alternators must be identical.
For example, if the grid sequence is R-Y-B, the incoming alternator must also have R-Y-B sequence.
4. Zero Phase Angle Difference
The corresponding phase voltages must be in phase at the instant of circuit-breaker closing.
This ensures minimum voltage difference across the breaker contacts.