hamburger menu
All Coursesall course arrow
adda247
reward-icon
adda247
    arrow
    arrow
    arrow
    The cost of construction including all the expenditure incurred from beginning to the completion of work is called as-
    Question

    The cost of construction including all the expenditure incurred from beginning to the completion of work is called as-

    A.

    Approximate cost

    B.

    Capital cost

    C.

    Labour cost

    D.

    Material cost

    Correct option is B


    The term capital cost refers to the total expenditure incurred from the beginning to the completion of a construction project. It includes all costs associated with the construction, such as materials, labor, overheads, and other related expenses.
    Approximate cost: Usually refers to a rough estimate of the cost, not the total expenditure.
    Labour cost: Refers specifically to the cost associated with the workforce involved in the construction.
    Material cost: Refers to the cost of the materials used in construction.
    Capital cost: Correct, as it encompasses all costs from the start to the completion of the project.
    Therefore, the correct answer is (b) Capital cost.

    test-prime-package

    Access ‘RRB JE Civil Engineering’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    383k+ students have already unlocked exclusive benefits with Test Prime!
    test-prime-package

    Access ‘RRB JE Civil Engineering’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    383k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow