Correct option is A
Solution:
From the table ; The Expenditure of the different sectors
Planning/Design:
Estimated: 87000 × 20 = 1740000
Actual: 87000 × 30 = 2610000
Increase: 2610000 − 1740000 = 870000
Construction:
Estimated: 805000 × 500 = 402500000
Actual: 805000 × 650 = 523250000
Increase: 523250000 − 402500000 = 120750000
Setting Pipelines:
Estimated: 610000 × 60 = 36600000
Actual: 610000 × 80 = 48800000
Increase: 48800000 − 36600000 = 12200000
Painting:
Estimated: 520000 × 30 = 15600000
Actual: 520000 × 40 = 20800000
Increase: 20800000 − 15600000 = 5200000
From the above , we can see that in Construction the Difference between Estimated and actual expenditure in maximum.