Correct option is B
In project management, slack, also known as float, is the amount of time that a task can be delayed without causing a delay to subsequent tasks or the overall project completion date. Specifically, slack is calculated as the difference between the latest allowable start time and the earliest expected start time for a task. If a task has zero slack, it is on the critical path, meaning any delay in this task will directly delay the project's completion.