    S can finish a piece of work in 12 days. He works for 4 days and R finishes the remaining work in 12 days. In how many days can they finish the work t
    Question

    S can finish a piece of work in 12 days. He works for 4 days and R finishes the remaining work in 12 days. In how many days can they finish the work together?

    A.

    7.2

    B.

    6.5

    C.

    7.5

    D.

    7

    Correct option is A

    7.2

    Free Tests

    Free
    Must Attempt

    Punjab Police Constable Paper-I & II PYP (Held on 30th July 2024 Shift 1)

    languageIcon English
    • pdpQsnIcon150 Questions
    • pdpsheetsIcon150 Marks
    • timerIcon180 Mins
    languageIcon English
    Free
    Must Attempt

    Punjab Police Constable Paper-I & II PYP (Held on 6th Aug 2024 Shift 1)

    languageIcon English
    • pdpQsnIcon150 Questions
    • pdpsheetsIcon150 Marks
    • timerIcon180 Mins
    languageIcon English
    Free
    Must Attempt

    PSSSB Clerk 2022-23 Mock 01

    languageIcon English
    • pdpQsnIcon150 Questions
    • pdpsheetsIcon150 Marks
    • timerIcon150 Mins
    languageIcon English

    Similar Questions