S can finish a piece of work in 12 days. He works for 4 days and R finishes the remaining work in 12 days. In how many days can they finish the work t
Question

S can finish a piece of work in 12 days. He works for 4 days and R finishes the remaining work in 12 days. In how many days can they finish the work together?

A.

7.2

B.

6.5

C.

7.5

D.

7

Correct option is A

7.2

Free Tests

Free
Must Attempt

Punjab Police Constable Paper-I & II PYP (Held on 30th July 2024 Shift 1)

languageIcon English
  • pdpQsnIcon150 Questions
  • pdpsheetsIcon150 Marks
  • timerIcon180 Mins
languageIcon English
Free
Must Attempt

Punjab Police Constable Paper-I & II PYP (Held on 6th Aug 2024 Shift 1)

languageIcon English
  • pdpQsnIcon150 Questions
  • pdpsheetsIcon150 Marks
  • timerIcon180 Mins
languageIcon English
Free
Must Attempt

PSSSB Clerk 2022-23 Mock 01

languageIcon English
  • pdpQsnIcon150 Questions
  • pdpsheetsIcon150 Marks
  • timerIcon150 Mins
languageIcon English
test-prime-package

Access ‘Punjab Police’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
346k+ students have already unlocked exclusive benefits with Test Prime!

Similar Questions