P and Q working separately can complete a piece of work in 9 and 12 days, respectively. If they work for a day alternately , starting with P, in how m
Question
P and Q working separately can complete a piece of work in 9 and 12 days, respectively. If they work for a day alternately , starting with P, in how many days can the work be completed ?
A.
10
B.
21
C.
8
D.
9
Correct option is A
10