Meera, Nina and Seema can complete a piece of work in 9 days, 12 days and 18 days respectively. If they start with Nina, then Meera and then Seema wor
Question

Meera, Nina and Seema can complete a piece of work in 9 days, 12 days and 18 days respectively. If they start with Nina, then Meera and then Seema work alternately every third day, then in how many days will the work be completed?

A.

20 days

B.

14 days

C.

16 days

D.

12 days

Correct option is D

Let the total work is 36 Units (Lcm of 9, 12, 18)
Efficiency = Total work/ Total time
A's efficiency = 36/9 = 4
​B's efficiency = 36/12 = 3
C's efficiency = 36/18 = 2

=> A, B and C does work in three days = 4 + 3 + 2 = 9 units
=> Time taken to do 36 units = 36/9 = 4
But 9 Units done in 3 days
So, Actual time is 4 x 3 = 12 days

Free Tests

Free
Must Attempt

SBI PO Prelims Full Mock Test-01

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

SBI PO Prelims 2026 : Quantitative Aptitude Section Test 01

languageIcon English
  • pdpQsnIcon30 Questions
  • pdpsheetsIcon30 Marks
  • timerIcon20 Mins
languageIcon English
Free
Must Attempt

SBI PO Pre 2025 Memory Based Paper 4-Aug-2025-1st shift

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon60 Mins
languageIcon English

Similar Questions