Correct option is D
Let the total work is 36 Units (Lcm of 9, 12, 18)
Efficiency = Total work/ Total time
A's efficiency = 36/9 = 4
B's efficiency = 36/12 = 3
C's efficiency = 36/18 = 2
=> A, B and C does work in three days = 4 + 3 + 2 = 9 units
=> Time taken to do 36 units = 36/9 = 4
But 9 Units done in 3 days
So, Actual time is 4 x 3 = 12 days