Correct option is C
Correct Answer: (c) 2020
Explanation: Indian Railways had set March 2020 as the deadline to eliminate all Unmanned Level Crossings (UMLCs) on Broad Gauge (BG) routes. However, this task was completed ahead of schedule in January 2019 to enhance safety and prevent accidents. The removal of UMLCs significantly reduced railway-related accidents at level crossings, ensuring better safety for both rail and road users.
Key Points for Exam:
· Targeted Completion: March 2020
· Actual Completion: January 2019
· Reason: To improve railway safety and reduce accidents
· Outcome: Significant reduction in accident risks at level crossings