If the pessimistic estimate of a project is Rs. 12 Cr, the optimistic is Rs. 9 Cr and the most likely estimate is Rs. 10 Cr, then the expected value (
Question

If the pessimistic estimate of a project is Rs. 12 Cr, the optimistic is Rs. 9 Cr and the most likely estimate is Rs. 10 Cr, then the expected value (Rs. In Cr) would be

A.

10.16

B.

10

C.

11.42

D.

12

Correct option is A

test-prime-package

Access ‘SSC JE Civil’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
368k+ students have already unlocked exclusive benefits with Test Prime!
test-prime-package

Access ‘SSC JE Civil’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
368k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow