If the pessimistic estimate of a project is Rs. 12 Cr, the optimistic is Rs. 9 Cr and the most likely estimate is Rs. 10 Cr, then the expected value (
Question
If the pessimistic estimate of a project is Rs. 12 Cr, the optimistic is Rs. 9 Cr and the most likely estimate is Rs. 10 Cr, then the expected value (Rs. In Cr) would be