Identify the correctly matched pair(s) from the following based on the unit of measurement used for the estimation of different items of work. 1.
Question

Identify the correctly matched pair(s) from the following based on the unit of measurement used for the estimation of different items of work.
1. Stone slab in roof: square metres
2. Cutting of trees: tonnes
3. Lime concrete in foundation: cubic metres

A.

Only 1 and 2

B.

Only 1 and 3

C.

1, 2 and 3

D.

Only 2 and 3

Correct option is B



test-prime-package

Access ‘SSC JE Civil’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
test-prime-package

Access ‘SSC JE Civil’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow