    Identify the correct sequence of Controlling process: (A) Analysing deviations (B) Measurement of actual performance (C) Setting up standards
    Question

    Identify the correct sequence of Controlling process:
    (A) Analysing deviations
    (B) Measurement of actual performance
    (C) Setting up standards
    (D) Comparison of actual performance with standards
    Choose the correct answer from the options given below:

    A.

    (A), (B), (C), (D)

    B.

    (A), (C), (B), (D)

    C.

    (B), (A), (D), (C)

    D.

    (C), (B), (D), (A)

    Correct option is D

    Correct Sequence:
    (C) Setting up standards
    (B) Measurement of actual performance
    (D) Comparison of actual performance with standards
    (A) Analysing deviations