Identify the correct sequence of Controlling process: (A) Analysing deviations (B) Measurement of actual performance (C) Setting up standards
Question

Identify the correct sequence of Controlling process:
(A) Analysing deviations
(B) Measurement of actual performance
(C) Setting up standards
(D) Comparison of actual performance with standards
Choose the correct answer from the options given below:

A.

(A), (B), (C), (D)

B.

(A), (C), (B), (D)

C.

(B), (A), (D), (C)

D.

(C), (B), (D), (A)

Correct option is D

Correct Sequence:
(C) Setting up standards
(B) Measurement of actual performance
(D) Comparison of actual performance with standards
(A) Analysing deviations