For a particular project, six activities are to be carried out. The precedence relation and duration of activities are as per the following table. The
Question

For a particular project, six activities are to be carried out. The precedence relation and duration of activities are as per the following table. The minimum project completion time (in days) is 

Activity

Immediate predecessor

Duration (days)

A

--

6

B

A

5

C

A

8

D

B

11

E

C

6

F

D, E

7

A.

32

B.

27

C.

29

D.

30

Correct option is C

Draw the Network Diagram1. StartABDFEnd(Path: A-B-D-F, Duration: 6+5+11+7=29 days)2. StartACEFEnd(Path: A-C-E-F, Duration: 6+8+6+7=27 days)Identify the Critical PathThe longest path determines the project duration.A-B-D-F (29 days) is longer than A-C-E-F (27 days).Thus, the critical path is ABDF.Calculate Minimum Project Completion TimeThe project cannot be completed faster than the critical path duration:Minimum Completion Time=6 (A)+5 (B)+11 (D)+7 (F)=29 days\textbf{Draw the Network Diagram} \\1. \ \text{Start} \rightarrow A \rightarrow B \rightarrow D \rightarrow F \rightarrow \text{End} \\\text{(Path: A-B-D-F, Duration: } 6 + 5 + 11 + 7 = \textbf{29 days)} \\\\2. \ \text{Start} \rightarrow A \rightarrow C \rightarrow E \rightarrow F \rightarrow \text{End} \\\text{(Path: A-C-E-F, Duration: } 6 + 8 + 6 + 7 = \textbf{27 days)} \\\\\textbf{Identify the Critical Path} \\\text{The longest path determines the project duration.} \\\textbf{A-B-D-F (29 days)} \text{ is longer than A-C-E-F (27 days).} \\\text{Thus, the critical path is } \boxed{A \rightarrow B \rightarrow D \rightarrow F}. \\\\\textbf{Calculate Minimum Project Completion Time} \\\text{The project cannot be completed faster than the critical path duration:} \\\text{Minimum Completion Time} = 6\,(\text{A}) + 5\,(\text{B}) + 11\,(\text{D}) + 7\,(\text{F}) = \boxed{29\, \text{days}}​​

test-prime-package

Access ‘ISRO Mechanical Engineering’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
test-prime-package

Access ‘ISRO Mechanical Engineering’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow