Correct option is C
Draw the Network Diagram1. Start→A→B→D→F→End(Path: A-B-D-F, Duration: 6+5+11+7=29 days)2. Start→A→C→E→F→End(Path: A-C-E-F, Duration: 6+8+6+7=27 days)Identify the Critical PathThe longest path determines the project duration.A-B-D-F (29 days) is longer than A-C-E-F (27 days).Thus, the critical path is A→B→D→F.Calculate Minimum Project Completion TimeThe project cannot be completed faster than the critical path duration:Minimum Completion Time=6(A)+5(B)+11(D)+7(F)=29days