Correct option is B
The load factor of a power station is defined as:Load Factor=Maximum DemandAverage LoadStep 1: Find Average LoadEnergy generated per day=2400 MWhAverage Load=TimeEnergy=24 h2400 MWh=100 MWStep 2: Use Load FactorGiven:Load Factor=0.50.5=Maximum Demand100Maximum Demand=0.5100=200 MW