Correct option is B
Given:
Pipe A usually fills a tank = 4 hours.
Due to leakage tank fill in = 5 hours
Formula Used:
Work = Time × Efficiency
Solution:
LCM of (4, 5) = 20 unit
Let the total capacity of tank be 20 unit
Efficiency of Pipe A =
Efficiency of Pipe A with leakage =
Efficiency of Leakage = 1 unit/hr
Leakage empties the tank in =