Correct option is C
Given:
A can finish the task in 16 days.
B can finish the same task in one- fourth the time taken by A, so B can finish the task in 4 days.
Formula Used:
Solution:
A's rate = of the task per day
B's rate = of the task per day
Total work done by A and B together in one day =
Thus, A and B together can finish of the task in one day.