Correct option is B
Given:
A can finish a work = 30 days
B finishes the remaining task in 24 days after A works for 6 days.
Formula used:
Total work = efficiency × time
Solution:
According to the question:
A can finish the task in 30 days, so the total work is:
Total work= A×30
In 6 days, A does
A 6
The remaining work =
Work done by B in 24 days
B completes the remaining A×24A \times 24 work in 24 days.
So, B’s efficiency is:
B = = A
Thus, A and B have the same efficiency.
Total time taken by A and B together-
When A and B work together, their combined efficiency is:
A+B = A+A= 2A
The total time taken to finish the task together is:
Total time = = = 15 days
A and B together can finish the task in 15 days.
Alternate Solution:
A's work rate = tasks per day, In 6 days, A completes = of the task
Remaining work = 1 - =
B finishes of the task in 24 days, so B's rate = = tasks per day
A + B's combined rate = + = tasks per day
Time for A and B together to finish the task =
= 15 days