    30 men can complete a piece of work in 20 days and 20 women can complete a piece of work in 50 days. 9 men and 6 women started the work. After work
    Question

    30 men can complete a piece of work in 20 days and 20 women can complete a piece of work in 50 days. 9
    men and 6 women started the work. After working for a few days, they were replaced by 18 men and 8 women
    who completed the remaining work in 4 days. How many days did the teams take to complete the task (all men
    are equally skilled and all women participating are equally skilled)

    A.

    8

    B.

    848/21

    C.

    932/21

    D.

    6

    Correct option is D

    6

    Free Tests

    Free
    Must Attempt

    SBI PO Prelims Full Mock Test-01

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon60 Mins
    languageIcon English
    Free
    Must Attempt

    SBI PO Prelims 2026 : Quantitative Aptitude Section Test 01

    languageIcon English
    • pdpQsnIcon30 Questions
    • pdpsheetsIcon30 Marks
    • timerIcon20 Mins
    languageIcon English
    Free
    Must Attempt

    SBI PO Pre 2025 Memory Based Paper 4-Aug-2025-1st shift

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon60 Mins
    languageIcon English

    Similar Questions