30 men can complete a piece of work in 20 days and 20 women can complete a piece of work in 50 days. 9 men and 6 women started the work. After work
Question

30 men can complete a piece of work in 20 days and 20 women can complete a piece of work in 50 days. 9
men and 6 women started the work. After working for a few days, they were replaced by 18 men and 8 women
who completed the remaining work in 4 days. How many days did the teams take to complete the task (all men
are equally skilled and all women participating are equally skilled)

A.

8

B.

848/21

C.

932/21

D.

6

Correct option is D

6

Free Tests

Free
Must Attempt

CBT-1 Full Mock Test 1 (Exam Level)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

CBT-1 Mathematics Section Test 1

languageIcon English
  • pdpQsnIcon30 Questions
  • pdpsheetsIcon30 Marks
  • timerIcon40 Mins
languageIcon English
Free
Must Attempt

CBT-1 General Awareness Section Test 1

languageIcon English
  • pdpQsnIcon40 Questions
  • pdpsheetsIcon40 Marks
  • timerIcon25 Mins
languageIcon English

Similar Questions