30 men can complete a piece of work in 20 days and 20 women can complete a piece of work in 50 days. 9
men and 6 women started the work. After work
Question
30 men can complete a piece of work in 20 days and 20 women can complete a piece of work in 50 days. 9
men and 6 women started the work. After working for a few days, they were replaced by 18 men and 8 women
who completed the remaining work in 4 days. How many days did the teams take to complete the task (all men
are equally skilled and all women participating are equally skilled)
A.
8
B.
848/21
C.
932/21
D.
6
Correct option is D