2 men and 7 boys can do a piece of work in 14 days, 3 men and 8 boys can do the same in 11 days. In how many days, 3 times the work can be completed b
Question

2 men and 7 boys can do a piece of work in 14 days, 3 men and 8 boys can do the same in 11 days. In how many days, 3 times the work can be completed by 8 men and 6 boys?

A.

21 days

B.

18 days

C.

24 days

D.

36 days

Correct option is A

Free Tests

Free
Must Attempt
Video Solutions

RBI Assistant Pre 2026 Full Mock Test -01

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

TNPSC Group 1 Services Prelims 2025 Official Paper (Held on 15 June 2025)

languageIcon English
  • pdpQsnIcon200 Questions
  • pdpsheetsIcon300 Marks
  • timerIcon180 Mins
languageIcon English
Free
Must Attempt

Development Administration in Tamil Nadu (All TNPSC PYQs) - 1

languageIcon English
  • pdpQsnIcon250 Questions
  • pdpsheetsIcon375 Marks
  • timerIcon300 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘TNPSC Group 1’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow