Q1. The time elapsed between the moment water added to the ordinary Portland cement and the time when the cement completely loses in plasticity and can resist certain definite pressure is termed as:
(a) Initial setting time
(b) Final setting time
(c) Hydration time
(d) Gestation period
Q2. The batching tolerance for cement as per IS 456 is
(a) ±1%
(b) ±1.5%
(c) ±2%
(d) ±3%
Q3. The bulking of sand occurs due to
(a) Air in voids
(b) Moisture in voids
(c) Surface tension
(d) Capillary action
Q4. Match the following
Environment of concrete Exposure condition
(A) Concrete continuously under 1. Very severe
Water
(B) Concrete completely immersed 2. Extreme severe
In sea water
(C) Concrete surface exposed 3. Severe
To sea water spray
(D) Surface of concrete member 4. Moderate
In tidal zone
(a) A-3, B-2, C-1, D-4
(b) A-4, B-2, C-1, D-3
(c) A-3, B-2, C-4, D-1
(d) A-4, B-3, C-1, D-2
Q5. Workability of concrete by slump test is expressed as
(a) mm
(b) mm²h
(c) mm/h
(d) minutes
Q6. Twisted bar has about _________ more yield stress than ordinary mild steel bar
(a) 10%
(b) 20%
(c) 35%
(d) 50%
Q7. The reinforcement in RCC takes –
(a) Tensile stress
(b) compressive stress
(c) Shear stress
(d) torsional stress
Q8. In limit state of collapse for direct compression, the maximum axial compressive strain in concrete is:
(a) 0.003
(b) 0.002
(c) 0.0035
(d) 0.006
Q9. Which of the following statements is incorrect?
(a) Higher Vee-Bee times shows lower workability.
(b) Higher slump shows higher workability
(c) Higher compacting factor shows higher workability.
(d) None of the above.
Q10. Under water concreting is done by:
(a) Dripping method
(b) Tremie method
(c) Cofferdam method
(d)All of the above
SOLUTION
S1. Ans.(b)
Sol. Initial setting time → it is the time lapsed between addition of water and the cement paste starts loosing its plasticity.
Final setting time → it is the time lapsed between the addition of water and the time when cement completely loses it’s plasticity.
S2. Ans.(c)
Sol.
Material Batching tolerance
Aggregate, Water, admixture cement ±3%
± 2%
S3. Ans.(b)
Sol. The presence of moisture in voids of sand increase the volume of sand.
S4. Ans.(d)
Sol.
S5. Ans.(a)
Sol. workability of concrete by slump test is expressed as ‘mm’. Slump test is used for concrete having size of aggregate up to 38 mm.
S6. Ans.(d)
Sol. twisted bar has 50% more yield stress then ordinary mild steel bar.
S7. Ans.(a)
Sol. Reinforcement in RCC structure takes tensile stress because concrete has very low strength in tension.
S8. Ans.(b)
Sol. in limit state of collapse for direct compression the maximum axial compression strain in concrete is 0.002.
S9. Ans.(d)
Sol.
S10. Ans.(b)
Sol. Tremie method is used for under water concreting